Apartment Finishing Timeline: How Long Does Each Stage Take?
One of the first questions clients ask any finishing company is about the apartment finishing timeline. The answer depends on area, level and organization. Here, GSC shares an approximate schedule for each stage and the most common causes of delay.
Average Finishing Duration
A medium-sized apartment usually takes two to five months. Simple finishes are faster, while complex decor and imported materials need more time.

Approximate Schedule by Stage
- Design and quantities: 1 to 3 weeks.
- Rough-in: 2 to 3 weeks.
- Plastering and waterproofing: 2 to 4 weeks.
- Ceilings and gypsum: 2 to 3 weeks.
- Flooring and tiling: 2 to 4 weeks.
- Painting, installations and handover: 3 to 5 weeks.
Common Causes of Delay
- Design changes during execution.
- Late material selection or supply.
- No written schedule or daily follow-up.
- Late payments or building permits.
Can Finishing Be Faster?
Yes, by fixing the design and materials before starting and running some work in parallel, such as fabricating the kitchen and doors during plastering. Drying times for plaster and waterproofing should never be cut.
How GSC Keeps Deadlines
GSC includes a schedule in the contract, follows up with a site engineer and regular reports, and prepares materials early. Learn about our finishing service.
Frequently Asked Questions
How long does a 100 sqm apartment take?
Usually two to four months depending on level and decor.
Which stage takes the longest?
Usually painting and final installations because of the detail involved.
Should the timeline be in the contract?
Yes. Start and handover dates, a stage schedule and a delay penalty should be included.